Southern Oaks Business Park

If you’ve driven through Plant City, Florida on I-4 lately, you may have seen us working on the Southern Oaks business park. For this 29-week tilt-wall project (May 2021 – December 2021) we poured the foundations, slabs and panels simultaneously for a 730,000 SF truck terminal.

STATS:

  • 31,000 man-hours and counting

  • 730,000 SF of interior SOG

  • 191,000 SF of tilt panels (146 panels)

  • 147,000 SF of 6” concrete paving

  • A 400 SF pump house

  • 29,000 SF of casting slab.

  • 10,900 SF of sidewalks

TEAM:

  • Alberic Correa – Tilt Wall Unit Leader

  • Jack Mills – Project Manager

  • Tony Martell – Superintendent

  • John Dycus – Superintendent